1949 JTR(Mad) 187
1950 AIR(Mad) 30 ; 1949 2 MLJ 298 ; 1950 KHC 5211
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Mr. Justice Mack, J.
Malladi Seetharama Sastri
Versus
The Hyderabad State represented by the General Manager, Nizam State Railway, Secunderabad (Deccan)
C.R.P. No. 1193 of 1947.
Decided On : 06 July 1949
Act Referred :LIMITATION ACT : Art.31
V. Subramaniam for Petitioner.
V.K. Ramanathan instructed by Messrs. King and Partridge for Respondent.
Judgment
The petitioner is the plaintiff, a merchant of Bezwada, who sued the Nizam State Railway of Hyderabad for the
recovery of Rs. 305 being the value of some machinery he consigned on 21st August, 1944, from Bezwada to the
Circar Engineering Company, Lahore. It is common ground that the goods had to be carried over three railways.
Plaintiff received from the consignee a letter Exhibit P-1 dated 7th November, 1944, to the effect that the goods had not
reached him. He sent a notice to the railway company on 8th February 1945, complaining that the goods had not been
delivered and asking for payment of their value. To this letter he was not vouchsafed any reply. He then, after going
through the necessary formalities, filed this suit on 31st October, 1945. The learned Subordinate Judge dismissed it as
time barred under Article 31 of the Limitation Act which prescribes as the period of limitation for a suit against a carrier
for compensation, non-delivery or delay in delivering goods one year from the date “when the goods ought to be
delivered”. The learned Subordinate Judge attached importance to the evidence of a parcels clerk of the Bezwada
railway station who deposed that it would normally take one week by passenger train and 15 days by goods train for a
consignment to reach Lahore. On this basis the Subordinate Judge held that the suit was filed out of time. The view
taken by him is obviously incorrect and cannot be suported.
Two limitation Articles which can govern this case are Article 30 which prescribes for suits against a carrier for
compensation for losing or injuring goods. one year from the date when the loss or injury occurred. In Madras and
Southern Mahratla Railway Co. v. Bhimappa1, a Bench of this Court observed as regards Article 30 that the burden of
proving when the goods were lost is on the railway company and that in that case they had not proved when they were
lost and there was nothing in the evidence to show that they were lost more than one year before the institution of the
suit. Those observations are relevant and pertinent to the facts of the present suit. As regards Article 31, the difficulty it
raises is that it fixes no specific time for the delivery of the goods, the ordinary rule being that goods have to be delivered
by a carrier within a reasonable time. What is a reasonable time has to depend on the facts of each case. In Jugal
Kishore v. Great Indian Peninsular Railway2, the plaintiff consigned goods on the 28th August, 1918, and filed his suit
for damages on the 31st March, 1920. For more than a year plaintiff had been put off by various statements on the part
of the railway companies to the effect that the matter was being enquired into. It was held that the suit was in time and
not barred, whether Article 30, or Article 31 was considered applicable to the facts. That suit was filed about a year
and eight months after the consignment, whereas the present suit was filed less than one year and three months after the
consignment. The learned Subordinate Judge relied on Palanichami Nadar v. Governor-General of India in Council3 for
the position that time would begin to run under Article 31 from the date of a definite refusal or declaration or inability by
the railway company to deliver the lost goods. But that construction of Article 31 has been obviously misapplied by the
learned Subordinate Judge to the facts of this suit. In the cases in which that construction was given, it merely enlarged
the period within which a suit should be brought from the date on which, after a protracted correspondence with the
railway company, they expressed inability to give delivery of the goods for some reason or other. In the present case,
the railway company did not even accord the plaintiff the courtesy of a reply to his original letter of complaint. In fact the
decision in Palanichami Nadar v. GovernorGeneral of India in Council3 gives very strong support following as it does,
Jugal Kishore v. Great Indian Peninsular Railway2 and Madras and Southern Mahratta Railway v. Bhimappa1, to the
present case of the plaintiff. It has also to be remembered that in 1944 railways were afflicted by war conditions and
congestion in transit, and two months and 16 days could not be, in any event, considered to be an unreasonable period
within which a railway company ought to have delivered the goods. When the plaintiff received the letter Exhibit P-1
from his consignee in Lahore that the goods had not yet reached there, he can scarcely be blamed for giving a little
further time before making his complaint to the railway company. In any event the suit was filed within a year of Exhibit
P-1. There is no substance in this technical plea of limitation taken on behalf of the railway. Nor can I see any substance
in another technical plea to the effect that the railway company has not been correctly impleaded in the suit. The
defendant was originally impleaded as the General Manager of the Nizam State Railway and this, on objection being
taken by the defendant, was amended to Hyderabad State represented by the General Manager of the Nizam State
Railway. Even this amended description of the defendant is now objected to by the learned advocate for the respondent
railway on grounds which I am unable to appreciate. It is not disputed, as the learned Subordinate Judge has also found,
that the value of the consignment of machinery is Rs. 300.
The petition is allowed with costs and the suit decreed as prayed for against the defendant railway also with full costs.
V.S. ----- Petition allowed.